Spikes
A short, timeboxed piece of research to reduce uncertainty before committing to a bigger item.
What it is
A spike is a short, time-boxed piece of investigation to answer a question or reduce uncertainty before committing to the real work.
When to use it
When the team can't estimate or plan an item because of a technical or product unknown.
Why it works
Some work can't be estimated or planned until you learn something. A spike buys that knowledge cheaply instead of guessing.
Do
- A spike without a time box turns into a project.
Don't
- Spikes that never end.
- Using spikes to avoid delivering anything usable.
Step by step
- Write the question What exactly do we need to learn?
- Set a time box Hours or a few days, not open-ended.
- Define the output A decision, a small prototype, an estimate.
- Do the investigation Only enough to answer the question.
- Share and decide Use what you learned to plan the real work.