Hospital booking system 42 questions 5 phases
CareSlot: a Product Owner case study St Mary's Hospital books outpatient appointments by phone, and patients wait 20 minutes on hold. You're the new Product Owner of CareSlot, the online booking system. Doctors, nurses, IT security and patients all care deeply, and they don't agree.
What this case study tests
Conflicting stakeholders Refinement & acceptance criteria Abandoning a Product Goal Privacy & quality
You're the Product Owner. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Team
Axel (Scrum Master) Coaches the team Ana (Developer) Front end, accessibility Aron (Developer) Hospital systems integration Stakeholders
Albert (Hospital Director) Sponsor and budget Ada (Head Nurse) Runs the wards Ahmed (Cardiologist) Busiest clinic Amber (IT Security Lead) Patient data Alma (Patient) Books several times a year CareSlot
Getting started Your first week at St Mary's
Question 1 of 42 Choose 1
Albert (Hospital Director) Phone booking is chaos. Patients are furious. Fix it, Aria.
What is your first step? Write a full specification first, so every department signs off Incorrect. A big upfront spec assumes you already know the answers.Understand patients, staff and the real problem before building Correct. Right. You can only maximise value once you understand the people and the problem.Ask the Developers to copy another hospital's working booking site Incorrect. Their solution may not fit your patients or hospital.
Learn it on Day 1: You're hired
Check answer
Question 2 of 42 Choose 1
Ada (Head Nurse) Nurses need triage first. Ahmed (Cardiologist) wants doctors to control their own calendars first. We can't both be first.
How do you decide? Listen to both, weigh the outcome for patients, order by value and explain why Correct. Right. You decide, transparently and with reasons.Go with the cardiologist: consultants carry clinical responsibility Incorrect. Seniority isn't value.Build half of each at the same time, so neither group feels ignored Incorrect. Splitting focus delays value for everyone.
Learn it on Day 2: Meet the stakeholders
Check answer
Question 3 of 42 Choose 2
Axel (Scrum Master) Let's map your stakeholders by influence and interest.
Which two engagement choices make sense? Albert (Hospital Director): high influence and interest, manage closely Correct. Correct.Patients like Alma: high interest, little influence, keep them involved Correct. Correct. They're the users, so their feedback matters a lot.Patients can be ignored: they don't fund the project at all Incorrect. Users decide whether the product succeeds.Give every stakeholder exactly the same time and attention Incorrect. Mapping exists so you can engage differently.
Learn it on Day 2: Meet the stakeholders
Check answer
Question 4 of 42 True or false
Albert (Hospital Director) You must be writing every backlog item yourself. That's a lot!
True or false: the Product Owner must personally write every Product Backlog item. True Incorrect. The Product Owner may have others do it, but remains accountable.False Correct. Correct. Delegation is allowed; accountability isn't transferred.
Learn it on Day 13: Questions from the team
Check answer
Question 5 of 42 Choose 1
Aria (Product Owner) Time to set a Product Goal.
Which is the best Product Goal? “Replace phone booking with online software by the end of the year.” Incorrect. Describes the solution, not the outcome.“Deliver all 12 planned modules on time and within the agreed budget.” Incorrect. That's a work plan, not a goal.“Patients can book, change or cancel an appointment online in two minutes.” Correct. Right. A clear future state focused on the user.
Learn it on Day 3: Shape the vision
Check answer
Question 6 of 42 Choose 1
Amber (IT Security Lead) Patient data must be encrypted and every access logged. Always.
Where does this belong? In a dedicated security phase at the end, testing the whole system Incorrect. Late security means unsafe Increments in between.With each Developer, who knows which features touch patient data Incorrect. Quality doesn't decrease. Patient data is critical.In the Definition of Done, so that every Increment always meets it Correct. Right. Non-negotiable quality rules belong in the Definition of Done.
Learn it on Day 5: Agree how the team will work
Check answer
Question 7 of 42 Choose 1
Axel (Scrum Master) The hospital wants to put 14 people in your Scrum Team.
What's the best advice? Typically 10 or fewer; consider two teams sharing one Product Backlog and one Product Owner Correct. Right. Smaller teams communicate better.Any size works: a bigger team means more hands, and Scrum doesn't set a limit Incorrect. The Scrum Guide suggests typically 10 or fewer people.Keep 14 but drop the Scrum Master, so there's one more Developer and the team stays manageable Incorrect. The Scrum Master is an essential accountability.
Learn it on Day 25: Product complete
Check answer
Question 8 of 42 Choose 2
Axel (Scrum Master) How can I help you as Product Owner?
Which two are ways the Scrum Master serves the Product Owner? Helping find techniques for the Product Goal and backlog management Correct. Correct.Facilitating collaboration with stakeholders when it's needed Correct. Correct.Ordering the Product Backlog on your behalf when you're busy Incorrect. Ordering stays your accountability.Approving your decisions before you share them with others Incorrect. The Scrum Master doesn't approve Product Owner decisions.
Learn it on Day 2: Meet the stakeholders
Check answer
Question 9 of 42 Choose 1
Ana (Developer) This backlog item says “Easy booking”. We can't build or test that.
What do you do? Let the Developers decide what “easy” means as they build it Incorrect. Guessing leads to rework.Refine it with the Developers: split it, then add clear acceptance criteria Correct. Right. Refinement makes items clear enough to be Done in a Sprint.Write a detailed specification of every booking screen first Incorrect. Detail should be just enough and discussed, not dumped.
Learn it on Day 5: Agree how the team will work
Check answer
Question 10 of 42 Choose 1
Albert (Hospital Director) I'll give the Developers their tasks each week, and the hospital's IT security team will review the whole system at the end, before launch.
What do you propose instead? Accept: the director knows the hospital, and a final review has always protected data Incorrect. Knowing the hospital doesn't make him the right person to plan the Developers' daily work.Agree goals with him; the self-managing Developers plan their work, with security in every Sprint Correct. Right. A cross-functional team builds security in each Sprint; a review only at the end finds problems in a system holding patient data when they are most expensive to fix.Accept the weekly tasks but drop the final security review, as patients need it soon Incorrect. Patient data needs security checks; the point is to build them in, not drop them.
Learn it on Day 11: Sprint 2 Planning
Check answer
CareSlot
Sprint 1 Goal: patients can see free slots and book a cardiology appointment
Question 11 of 42 Choose 1
Axel (Scrum Master) How long can Sprint Planning take?
What does the Scrum Guide say? At most 8 hours for a one-month Sprint; shorter Sprints usually need less Correct. Correct.One full working day, whatever the Sprint length, so nothing is rushed Incorrect. The 8-hour maximum is for a one-month Sprint.There's no limit: it takes as long as the team needs to agree a plan Incorrect. All Scrum events are timeboxed.15 minutes, like the Daily Scrum, to leave more time for the work Incorrect. That's the Daily Scrum.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 12 of 42 Choose 1
Ada (Head Nurse) The story just says “send reminders”. When, how, to whom?
How do you make it testable? Leave the details to the Developers, who know the text system Incorrect. The Developers build it, but what counts as done for this item is agreed with you, so it can be checked.Agree acceptance criteria: one text at 6 p.m. with time and ward Correct. Right. Clear acceptance criteria (for example Given / When / Then) make the behaviour checkable and shared.Add “reminders are sent” to the Definition of Done for every item Incorrect. The Definition of Done is for all items. Item-specific rules are acceptance criteria.
Learn it on Day 13: Questions from the team Technique: Acceptance criteria and Given/When/Then
Check answer
Question 13 of 42 Choose 1
Ahmed (Cardiologist) We need video consultations now! Put them in this Sprint.
The Sprint Goal is still valid. What do you do? Swap the Sprint's work for video consultations: it's clinical need Incorrect. That would abandon a valid Sprint Goal.Tell him it's out of scope: the project is booking, not consultations Incorrect. Not now is different from never.Add video consultations to the Product Backlog, ordered with the rest Correct. Right. No changes that endanger the Sprint Goal.
Learn it on Day 8: A request on the go
Check answer
Question 14 of 42 Choose 1
Albert (Hospital Director) I'd like to join the Daily Scrum every morning to keep an eye on things.
What do you suggest? Let him attend and ask questions, since a director showing interest motivates the team Incorrect. It would become a status meeting for a manager.It's the Developers' event; offer the backlog and the Sprint Review for transparency instead Correct. Right. Protect the event's purpose and still be transparent.Replace it with a weekly status report for him, so he isn't kept waiting for information Incorrect. It's a daily planning event for the Developers.
Learn it on Day 7: A blocker on day two
Check answer
Question 15 of 42 Choose 1
Albert (Hospital Director) Fifteen requests from three hospitals. Which first? I need a reason the board will accept.
Which technique helps you compare and explain the order? First come, first served: fair to every hospital and easy to explain Incorrect. Arrival order has nothing to do with value.Use a value vs effort grid with rough sizes, then order and explain Correct. Right. It's fast, visual and easy to explain; you still decide the final order.Let each hospital vote and build the winner, so it looks democratic Incorrect. Votes are input, not your accountability.
Learn it on Day 4: Build and order the backlog Technique: Value vs effort
Check answer
Question 16 of 42 Choose 1
Aron (Developer) The old hospital system has no documentation. Integration may take longer than planned.
What should happen? Collaborate with the Developers to renegotiate scope, keeping the Sprint Goal intact Correct. Right.Hold the team to the original scope, since the board was promised these features Incorrect. Ignoring new information isn't empirical.Relax the logging rules for this one integration to save time, then add them back later Incorrect. Quality doesn't decrease.
Learn it on Day 13: Questions from the team
Check answer
Question 17 of 42 Choose 1
Ana (Developer) Booking works, but the accessibility check in our Definition of Done isn't finished.
Is the item Done? No: it doesn't meet the Definition of Done, so it isn't in the Increment Correct. Right.Yes: it works, and accessibility can be added in a later Sprint Incorrect. Done means the whole Definition of Done is met.
Learn it on Day 24: Final checks
Check answer
Question 18 of 42 Choose 1
Ada (Head Nurse) At the Review: nurses need to see bookings in their own ward view.
What do you do? Note it for later: the Review is for showing work, not changing plans Incorrect. Feedback should shape the backlog.Promise it for next Sprint on the spot, so the nurses leave confident Incorrect. First weigh it against everything else.Discuss it in the Review and adapt the Product Backlog accordingly Correct. Right. That's what the Sprint Review is for.
Learn it on Day 10: Review and Retrospective
Check answer
CareSlot
Sprint 2 Goal: patients can change or cancel appointments and get reminders
Question 19 of 42 True or false
Ahmed (Cardiologist) If I think a Sprint is going badly, can I stop it?
True or false: only the Product Owner may cancel a Sprint. True Correct. Correct, and only if the Sprint Goal becomes obsolete.False Incorrect. No one else has that authority.
Learn it on Day 8: A request on the go
Check answer
Question 20 of 42 Choose 1
Alma (Patient) The buttons are so small. I gave up and phoned instead.
What does this feedback mean for you? Lost value: order accessibility high, and strengthen the Definition of Done Correct. Right. If users can't use it, there's no value.Add a phone number on every page, so patients who struggle can still call Incorrect. The product must work for its users.Nothing yet: one patient's experience isn't enough to change the design Incorrect. A big group of patients is affected.
Learn it on Day 4: Build and order the backlog
Check answer
Question 21 of 42 Choose 2
Axel (Scrum Master) Let's check our understanding of the Increment.
Which two statements are true? It must meet the Definition of Done Correct. Correct.It's additive to all prior Increments Correct. Correct, and thoroughly verified so they work together.Only one Increment can be made a Sprint Incorrect. Several can be created within a Sprint.Albert (Hospital Director) approves it Incorrect. There is no approval gate.
Learn it on Day 15: Release decision
Check answer
Question 22 of 42 Choose 1
Ahmed (Cardiologist) Ada (Head Nurse) and I disagree on the reminder text again. Who has the final say?
Who decides what goes into the product? Whoever is more senior clinically, since patient safety depends on them Incorrect. Seniority doesn't decide: the Product Owner decides after listening to both.The Product Owner, after listening carefully to both of them Correct. Right. You're accountable for the product's value.The Scrum Master, who can facilitate an agreement both accept Incorrect. The Scrum Master facilitates, not decides content.
Learn it on Day 12: The CEO has an idea
Check answer
Question 23 of 42 Choose 1
Axel (Scrum Master) Our last Sprint Review took five hours and became a slideshow.
What's wrong? It should be a working session, at most 4 hours for a month Correct. Right. The Scrum Master helps keep events productive and within the timebox.Nothing: a longer Review shows stakeholders everything Incorrect. Events are timeboxed for a reason.Slides were the problem: send a written report instead Incorrect. The Review is essential for inspection and adaptation.
Learn it on Day 10: Review and Retrospective
Check answer
Question 24 of 42 Choose 1
Albert (Hospital Director) The team's velocity fell from 30 to 22. Are they getting lazy?
How do you respond? Compare it with the other team's velocity, to see if it's unusual Incorrect. Velocity isn't comparable between teams.Ask for a plan to get back to 30 points, since the board tracks it Incorrect. That just inflates estimates.Velocity is a planning aid; look at the outcomes and impediments Correct. Right. Value is measured by outcomes, and drops usually have causes worth inspecting.
Learn it on Day 16: Learning from real users
Check answer
Question 25 of 42 Choose 1
Albert (Hospital Director) Reminders cut no-shows by 15% in testing. Release now or wait?
What do you decide? Release now: it's Done and valuable Correct. Right.Wait for the whole system to be done Incorrect. Value delayed is value lost.
Learn it on Day 15: Release decision
Check answer
Question 26 of 42 True or false
Abel (Developer) We found a better way to run code reviews. Should we wait to start?
True or false: improvements from a Retrospective must wait until next quarter. True Incorrect. Improvements are addressed as soon as possible, even in the next Sprint.False Correct. Correct.
Learn it on Day 20: Release v1.1
Check answer
CareSlot
Sprint 3 Goal: family doctors can refer patients directly
Question 27 of 42 Choose 1
Albert (Hospital Director) Big news: the national health service will handle all GP referrals for every hospital within three months.
Your Product Goal is “GPs refer patients directly through CareSlot”. What do you do? Keep building: the national system may slip, and work has started Incorrect. Building something obsolete wastes value.Abandon this Product Goal and set a new one that fits CareSlot Correct. Right. A Product Goal is fulfilled or abandoned before the next one.Pursue both the old and a new goal, in case national plans change Incorrect. One Product Goal at a time.
Learn it on Day 23: Thinking beyond v2
Check answer
Question 28 of 42 Choose 1
Aron (Developer) And our current Sprint Goal is the GP referral form.
What happens to this Sprint? You may cancel the Sprint because its goal is obsolete, then start a new Sprint Planning Correct. Right.The Developers cancel it, since they're the ones who can see the work is no longer needed Incorrect. Only the Product Owner may cancel a Sprint.Finish it anyway: the form might still be useful, and Sprints should always run to the end Incorrect. Finishing obsolete work wastes time.
Learn it on Day 8: A request on the go
Check answer
Question 29 of 42 Choose 2
Axel (Scrum Master) Let's recap Sprint cancellation.
Which two statements are true? Only the Product Owner has the authority to cancel a Sprint Correct. Correct.A Sprint may be cancelled if its Sprint Goal becomes obsolete Correct. Correct.The Scrum Master may cancel it if the team is unhappy with it Incorrect. Not the Scrum Master's authority.Stakeholders vote together on whether to cancel the Sprint Incorrect. Stakeholders have no such authority.
Learn it on Day 8: A request on the go
Check answer
Question 30 of 42 Choose 3
Axel (Scrum Master) What we just did was empiricism in action.
Choose the three pillars of empiricism. Transparency Correct. Correct.Inspection Correct. Correct.Adaptation Correct. Correct.Prediction Incorrect. Scrum is empirical, not predictive.
Learn it on Day 16: Learning from real users
Check answer
Question 31 of 42 Choose 1
Amber (IT Security Lead) A bug in the live system shows patient names in a log file.
What do you do? Add it to the backlog for next Sprint: the log is only internal Incorrect. A live privacy issue can't wait.Fix it quietly, so patients aren't alarmed over an unread log Incorrect. Transparency is essential, especially with patient data.Make it top priority and transparent; the Developers replan Correct. Right. Safety and quality come first.
Learn it on Day 9: A tool problem
Check answer
Question 32 of 42 True or false
Abel (Developer) The old booking code is full of shortcuts. It's slowing us down.
True or false: technical debt is purely a Developer concern. True Incorrect. Debt reduces your ability to deliver value, so it's a product concern too.False Correct. Correct. Keep it transparent and order work to reduce it.
Learn it on Day 19: The team wants to refactor
Check answer
Question 33 of 42 Choose 2
Axel (Scrum Master) What are the Developers accountable for?
Choose two. Creating the plan for the Sprint, the Sprint Backlog Correct. Correct.Holding each other accountable as professionals Correct. Correct.Ordering the Product Backlog by business value Incorrect. That's the Product Owner.Accepting the work on behalf of stakeholders Incorrect. Not a Developer accountability.
Learn it on Day 9: A tool problem
Check answer
Question 34 of 42 Choose 1
Ada (Head Nurse) Nurses need a short training before the new ward view goes live.
How do you handle it? Put it in the release plan and keep it visible in the backlog Correct. Right. Value only arrives when people can use the product.Release anyway: the IT department will sort out the rest Incorrect. Confused staff can hurt patients.
Learn it on Day 15: Release decision
Check answer
Question 35 of 42 Choose 1
Aron (Developer) Ahmed (Cardiologist) keeps asking me directly for features for his clinic. I've been quietly fitting them into the Sprint.
What do you do? Let it continue: the cardiologist is a key user, and small favours keep him onside Incorrect. Side deals make priorities invisible and unfair to other stakeholders.Remind the whole team firmly that side requests aren't allowed, so it stops Incorrect. Blame discourages people from being open next time; the problem is how requests arrive.Thank Aron and bring it into the open: requests go to the Product Backlog Correct. Right. Openness about who asks for what keeps every clinic treated with respect; hidden side requests quietly take capacity from the agreed goal.
Learn it on Day 22: Overtime pressure
Check answer
CareSlot
Sprint 4 and beyond Goal: patients can see live waiting times
Question 36 of 42 Choose 1
Albert (Hospital Director) Commit to all 20 regional features by June. The board needs certainty.
How do you respond? Commit to all 20 by June, as the director expects Incorrect. False certainty leads to cut corners or broken promises.Share an evidence-based forecast and keep the scope flexible Correct. Right. Complex work can't be fixed in advance.
Learn it on Day 14: Where are my promo codes?
Check answer
Question 37 of 42 Choose 1
Aria (Product Owner) You must tell Albert (Hospital Director) that regional data won't be ready by June.
Which Scrum value does this take most? Focus, on the remaining work Incorrect. Important, but not the key value here.Courage, to say it honestly Correct. Right. Doing the right thing and sharing hard news openly takes courage.Commitment, to the promised date Incorrect. Commitment in Scrum is to goals and each other, not to impossible dates.
Learn it on Day 12: The CEO has an idea
Check answer
Question 38 of 42 Choose 1
Albert (Hospital Director) Other departments want to try Scrum too.
Who leads and coaches that adoption? Axel (Scrum Master): serving the organisation is part of the role Correct. Right.The Product Owner, since adoption is about how products get built Incorrect. Not your accountability.The IT Security Lead, who already works across every department Incorrect. Not their role.
Learn it on Day 7: A blocker on day two
Check answer
Question 39 of 42 Choose 1
Amber (IT Security Lead) Every release needs a three-month approval board, so features wait for months.
Which Evidence-Based Management area is this hurting? Current Value: what patients get from the product today Incorrect. The delay is mainly about time to market.None: approval boards are a normal step in hospitals Incorrect. Long delays reduce value and learning.Time to Market: how fast new value reaches patients Correct. Right. How quickly value reaches users.
Learn it on Day 16: Learning from real users
Check answer
Question 40 of 42 Choose 2
Albert (Hospital Director) How will we show the board CareSlot was worth it?
Which two are good outcome measures? A lower rate of missed appointments Correct. Correct, an outcome for the hospital.Average time for a patient to book Correct. Correct, an outcome for patients.The number of booking screens built Incorrect. Output.Hours the team worked each week Incorrect. Effort, not value.
Learn it on Day 3: Shape the vision
Check answer
Question 41 of 42 Choose 1
Alma (Patient) Could I also renew my prescriptions online?
What does this request represent? Out of scope: CareSlot is for appointments, not prescriptions Incorrect. Products evolve with user needs.Unrealised value worth validating for a future Product Goal Correct. Right.A request to build next Sprint, since patients have asked for it directly Incorrect. Validate and order it first.
Learn it on Day 23: Thinking beyond v2
Check answer
Question 42 of 42 True or false
Albert (Hospital Director) Out of respect, just say yes to senior people.
True or false: a Product Owner should accept every request from senior stakeholders. True Incorrect. Respect means listening and explaining, not always agreeing.False Correct. Correct. Yes or no, always with a reason.
Learn it on Day 4: Build and order the backlog
Check answer