Commuter e-bike44 questions5 phases

Pedalo: a Product Owner case study

Pedalo is a young company building an affordable commuter e-bike. There's no code to ship every week: there are frames, batteries, suppliers with 12-week lead times and a safety certificate to earn. You're the Product Owner, and some engineers doubt Scrum works for hardware at all.

What this case study tests
Increments in hardwareLead times & suppliersSafety in the DoDCancelling a Sprint

You're the Product Owner. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Team
Amalia (Product Owner)You
Abe (Scrum Master)Coaches the team
Alvaro (Developer)Mechanical engineer
Anouk (Developer)Electronics engineer
Ash (Developer)Industrial designer
Stakeholders
Ambrose (Founder & CEO)Sponsor and investors
Alina (Supply Chain Manager)Suppliers and lead times
Armand (Safety Certification Lead)Legal safety standards
Avery (Bike Shop Owner)Retail partner
Aiko (Test Rider)Daily commuter
Pedalo

Getting started

Can Scrum build a bike?

Question 1 of 44

True or false
Alvaro (Developer)
We're engineers, not coders. Isn't Scrum just for software?

True or false: Scrum can only be used for software.

Learn it on Day 1: You're hired

Question 2 of 44

Choose 2
Abe (Scrum Master)
Let's be clear about who the Developers are on this team.

Which two people count as Developers?

Learn it on Day 1: You're hired

Question 3 of 44

Choose 1
Amalia (Product Owner)
Time to set a Product Goal.

Which is the best Product Goal?

Learn it on Day 3: Shape the vision

Question 4 of 44

Choose 1
Armand (Safety Certification Lead)
No bike reaches a rider unless it passes the e-bike safety standard.

How do you handle this?

Learn it on Day 5: Agree how the team will work

Question 5 of 44

Choose 1
Alina (Supply Chain Manager)
Motors take 12 weeks to arrive from the supplier.

How do long lead times affect the Product Backlog?

Learn it on Day 4: Build and order the backlog

Question 6 of 44

Choose 1
Ambrose (Founder & CEO)
Hardware is slow. Let's run three-month Sprints.

What's the best response?

Learn it on Day 5: Agree how the team will work

Question 7 of 44

Choose 1
Abe (Scrum Master)
What can count as an Increment for us?

Which is a valid Increment?

Learn it on Day 15: Release decision

Question 8 of 44

Choose 1
Avery (Bike Shop Owner)
My mechanics need bikes that are easy to service, or I won't stock them.

What do you do with this?

Learn it on Day 2: Meet the stakeholders

Question 9 of 44

Choose 1
Aiko (Test Rider)
I'd happily test early versions on my commute.

How do you learn what riders value before production?

Learn it on Day 16: Learning from real users

Question 10 of 44

Choose 1
Ambrose (Founder & CEO)
Our engineers are used to me assigning each part to a person. Shouldn't I keep doing that so the frame and motor get built?

What do you advise?

Learn it on Day 11: Sprint 2 Planning
Pedalo

Sprint 1

Goal: a rideable frame and motor prototype for first test rides

Question 11 of 44

Choose 1
Alvaro (Developer)
We can get the frame and motor mount Done this Sprint. Not the battery.

What do you do?

Learn it on Day 6: Sprint 1 Planning

Question 12 of 44

Choose 1
Anouk (Developer)
The motor controller samples are stuck in customs.

Who helps remove this impediment?

Learn it on Day 7: A blocker on day two

Question 13 of 44

Choose 1
Ambrose (Founder & CEO)
An investor wants a carbon-frame version for a demo next week. Add it now!

The Sprint Goal is still valid. What do you do?

Learn it on Day 8: A request on the go

Question 14 of 44

True or false
Ash (Developer)
Can we even show a physical prototype at a Sprint Review?

True or false: only finished products can be shown at a Sprint Review.

Learn it on Day 10: Review and Retrospective

Question 15 of 44

Choose 1
Alvaro (Developer)
The frame looks great, but the load test in our Definition of Done hasn't been run.

Is it Done?

Learn it on Day 24: Final checks

Question 16 of 44

Choose 1
Ambrose (Founder & CEO)
Investors want a goal for the quarter they can track.

Which is a good OKR?

Learn it on Day 3: Shape the vision

Technique: OKRs

Question 17 of 44

Choose 1
Aiko (Test Rider)
Rode it to work. The brakes feel weak going downhill.

What do you do?

Learn it on Day 10: Review and Retrospective

Question 18 of 44

Choose 1
Abe (Scrum Master)
In the Retrospective: test-lab bookings keep clashing between engineers.

What happens with this?

Learn it on Day 20: Release v1.1

Question 19 of 44

Choose 1
Ambrose (Founder & CEO)
Half the engineers are at the supplier's factory this week. Let's skip the Daily Scrum until they're back.

What do you suggest?

Learn it on Day 7: A blocker on day two
Pedalo

Sprint 2

Goal: a battery pack that gives 30 km in real rides

Question 20 of 44

Choose 1
Alina (Supply Chain Manager)
The battery supplier offers a big discount if we commit to 5,000 units now.

How do you decide?

Learn it on Day 17: A licence problem

Question 21 of 44

Choose 1
Anouk (Developer)
Real-world test: 22 km, not 30.

What's the empirical response?

Learn it on Day 16: Learning from real users

Question 22 of 44

True or false
Ambrose (Founder & CEO)
The range test failed. Doesn't that mean the Sprint failed?

True or false: a failed test means the Sprint must be cancelled.

Learn it on Day 8: A request on the go

Question 23 of 44

Choose 1
Anouk (Developer)
None of us really knows battery management systems.

What's the best way forward?

Learn it on Day 11: Sprint 2 Planning

Question 24 of 44

Choose 1
Armand (Safety Certification Lead)
The certification lab is booked up four months ahead.

What do you do?

Learn it on Day 17: A licence problem

Question 25 of 44

Choose 2
Abe (Scrum Master)
What belongs in Pedalo's Product Backlog?

Which two belong there?

Learn it on Day 4: Build and order the backlog

Question 26 of 44

Choose 1
Avery (Bike Shop Owner)
When can I put Pedalo bikes in my shop window?

How do you answer?

Learn it on Day 14: Where are my promo codes?

Question 27 of 44

Choose 1
Ash (Developer)
The quick-fix wiring harness takes 40 minutes to assemble per bike.

What is this, and what do you do?

Learn it on Day 19: The team wants to refactor

Question 28 of 44

Choose 1
Anouk (Developer)
“A battery that gives 30 km” is one big item, and the cells take 12 weeks to arrive from the supplier.

How do you refine it?

Learn it on Day 13: Questions from the team
Pedalo

Sprint 3

Goal: a pre-production bike that passes certification

Question 29 of 44

Choose 1
Ambrose (Founder & CEO)
Skip the second certification test. We need to hit spring.

What do you say?

Learn it on Day 9: A tool problem

Question 30 of 44

Choose 1
Alvaro (Developer)
I have to say it: the frame design won't pass. We need to redo it.

Which Scrum value is Alvaro (Developer) showing?

Learn it on Day 12: The CEO has an idea

Question 31 of 44

Choose 1
Alina (Supply Chain Manager)
Bad news: our motor supplier has gone bankrupt. That motor no longer exists.

The Sprint Goal is to certify the bike with that motor. What do you do?

Learn it on Day 8: A request on the go

Question 32 of 44

Choose 1
Ambrose (Founder & CEO)
Does this kill the whole product?

The Product Goal is 30 km to work, under €1,500.

Learn it on Day 23: Thinking beyond v2

Question 33 of 44

Choose 2
Abe (Scrum Master)
Let's look at value through Evidence-Based Management.

Every design change takes 10 weeks to test, and engineers spend most of their time fixing early prototypes. Which two areas suffer?

Learn it on Day 16: Learning from real users

Question 34 of 44

True or false
Armand (Safety Certification Lead)
Could I write the certification backlog items myself?

True or false: the Product Owner may delegate this but stays accountable.

Learn it on Day 13: Questions from the team

Question 35 of 44

Choose 1
Aiko (Test Rider)
Riders keep asking for a phone holder, gears, a basket and GPS. What's the smallest bike we can learn from?

What do you aim for first?

Learn it on Day 15: Release decision

Technique: Minimum viable product (MVP)

Question 36 of 44

Choose 1
Avery (Bike Shop Owner)
I want an exclusive deal: only my shops sell Pedalo for a year.

How do you approach this?

Learn it on Day 4: Build and order the backlog

Question 37 of 44

Choose 1
Ash (Developer)
Armand (Safety Certification Lead) found a weakness in the frame. Some of us think he's too strict and want to argue it past him.

What's the right stance?

Learn it on Day 22: Overtime pressure
Pedalo

Sprint 4 and beyond

Goal: the first 200 bikes in riders' hands

Question 38 of 44

Choose 1
Ambrose (Founder & CEO)
Ship 200 bikes now, or wait and launch 2,000?

What do you decide?

Learn it on Day 15: Release decision

Question 39 of 44

Choose 2
Ambrose (Founder & CEO)
How will we know Pedalo works?

Which two are good outcome measures?

Learn it on Day 3: Shape the vision

Question 40 of 44

Choose 1
Aiko (Test Rider)
Could it carry a child seat? Half my colleagues ask.

What does this represent?

Learn it on Day 23: Thinking beyond v2

Question 41 of 44

Choose 1
Ambrose (Founder & CEO)
We're starting a cargo-bike version with a second team.

If it's the same product, how is it organised?

Learn it on Day 25: Product complete

Question 42 of 44

Choose 1
Ambrose (Founder & CEO)
Two weekends of overtime before launch?

What do you and Abe (Scrum Master) advise?

Learn it on Day 22: Overtime pressure

Question 43 of 44

True or false
Abe (Scrum Master)
Looking back: was Scrum a good fit?

True or false: Scrum suited Pedalo because designing a new e-bike was full of uncertainty.

Learn it on Day 16: Learning from real users

Question 44 of 44

Choose 1
Ambrose (Founder & CEO)
The first Product Goal is achieved. What next?

What comes next?

Learn it on Day 23: Thinking beyond v2