City music festival45 questions5 phases

Harbourfest: a Product Owner case study

Harbourfest is a new three-day music festival on the city harbour, nine months away. The date can't move, the safety rules are strict, and sponsors want visibility. You're the Product Owner. This case also asks a mature question: where does Scrum help, and where is a simple plan enough?

What this case study tests
When Scrum fitsFixed datesSponsors vs audienceSafety first

You're the Product Owner. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Team
Avril (Product Owner)You
Aziz (Scrum Master)Coaches the team
Abby (Developer)Site production
Arvid (Developer)Artist booking
Ally (Developer)Marketing and ticketing
Stakeholders
Anthony (Festival Director)Sponsor and vision
Ayaan (City Events Officer)Licences and permits
Andrea (Sponsor Manager)Main sponsor's interests
Archer (Safety Officer)Crowd safety
Amelie (Festival-goer)Goes to three festivals a year
Harbourfest

Getting started

Where does Scrum fit a festival?

Question 1 of 45

Choose 1
Anthony (Festival Director)
The festival happens on three fixed days. Is Scrum even useful?

What's the most accurate view?

Learn it on Day 16: Learning from real users

Question 2 of 45

Choose 1
Avril (Product Owner)
Time to set a Product Goal.

Which is the best Product Goal?

Learn it on Day 3: Shape the vision

Question 3 of 45

Choose 1
Archer (Safety Officer)
Nothing reaches the public unless it meets crowd-safety rules.

Where does this belong?

Learn it on Day 5: Agree how the team will work

Question 4 of 45

Choose 1
Andrea (Sponsor Manager)
Our sponsor wants its logo on every single thing.

How do you treat this request?

Learn it on Day 4: Build and order the backlog

Question 5 of 45

Choose 1
Aziz (Scrum Master)
What could an Increment be before the festival?

Which is a valid Increment?

Learn it on Day 15: Release decision

Question 6 of 45

Choose 1
Ayaan (City Events Officer)
The city licence takes four months to process.

What does this mean for the backlog?

Learn it on Day 4: Build and order the backlog

Question 7 of 45

Choose 1
Amelie (Festival-goer)
What ruins festivals for me? Long queues for food and toilets.

How do you use this?

Learn it on Day 2: Meet the stakeholders

Question 8 of 45

Choose 2
Aziz (Scrum Master)
Who's on the Scrum Team?

Which two are Developers?

Learn it on Day 1: You're hired

Question 9 of 45

Choose 1
Anthony (Festival Director)
Let's do one Sprint per quarter.

What's the issue?

Learn it on Day 5: Agree how the team will work

Question 10 of 45

Choose 1
Anthony (Festival Director)
Ticketing, site design and marketing are three separate departments. Each delivers its part and we'll join them up at the end.

What do you propose for the parts run with Scrum?

Learn it on Day 11: Sprint 2 Planning
Harbourfest

Sprint 1

Goal: early-bird tickets on sale and 2,000 sold

Question 11 of 45

Choose 1
Ally (Developer)
We can launch tickets this Sprint, but not the merchandise shop.

What do you do?

Learn it on Day 6: Sprint 1 Planning

Question 12 of 45

Choose 1
Ally (Developer)
The ticketing provider hasn't activated our account.

Who helps remove this impediment?

Learn it on Day 7: A blocker on day two

Question 13 of 45

Choose 1
Anthony (Festival Director)
Announce the headliner this Sprint! I'm almost sure we'll get them.

The headliner isn't confirmed. What do you do?

Learn it on Day 8: A request on the go

Question 14 of 45

Choose 1
Ally (Developer)
The ticket page works, but the accessibility check isn't done.

Is it Done?

Learn it on Day 24: Final checks

Question 15 of 45

Choose 1
Ally (Developer)
We sold 600 tickets, not 2,000.

What's the empirical response?

Learn it on Day 16: Learning from real users

Question 16 of 45

Choose 2
Aziz (Scrum Master)
Who attends the Sprint Review?

Which two should be there?

Learn it on Day 10: Review and Retrospective

Question 17 of 45

Choose 1
Aziz (Scrum Master)
Retrospective: we lost time waiting for supplier quotes.

What's a good improvement?

Learn it on Day 20: Release v1.1

Question 18 of 45

True or false
Anthony (Festival Director)
Can the sponsor stop a Sprint if they're unhappy?

True or false.

Learn it on Day 8: A request on the go

Question 19 of 45

Choose 1
Abby (Developer)
In Sprint Planning, Andrea (Sponsor Manager) wants us to take on sponsor banners as well as early-bird tickets. We don't think we can do both.

How is it settled?

Learn it on Day 6: Sprint 1 Planning

Question 20 of 45

Choose 1
Anthony (Festival Director)
Everyone's so busy. Can we skip the Daily Scrum on days when nothing much has changed?

What do you say?

Learn it on Day 7: A blocker on day two
Harbourfest

Sprint 2

Goal: festival-goers can plan their weekend

Question 21 of 45

Choose 1
Amelie (Festival-goer)
I'd buy a ticket if I knew how to get there and where to stay.

What do you do?

Learn it on Day 16: Learning from real users

Question 22 of 45

Choose 1
Arvid (Developer)
Two artists cancelled. Our plan for the line-up page has to change.

What should happen?

Learn it on Day 13: Questions from the team

Question 23 of 45

True or false
Andrea (Sponsor Manager)
Could we skip the safety review of the sponsor stage to save time?

True or false: quality and safety may be lowered to meet a Sprint Goal.

Learn it on Day 9: A tool problem

Question 24 of 45

Choose 1
Abby (Developer)
None of us has planned a site this big.

What's the best way forward?

Learn it on Day 11: Sprint 2 Planning

Question 25 of 45

Choose 2
Aziz (Scrum Master)
Let's check our understanding.

Which two are true about the Product Backlog?

Learn it on Day 4: Build and order the backlog

Question 26 of 45

Choose 1
Ayaan (City Events Officer)
The city wants a progress update.

What's the most transparent option?

Learn it on Day 14: Where are my promo codes?

Question 27 of 45

Choose 1
Anthony (Festival Director)
Will we sell out by the summer?

How do you answer?

Learn it on Day 14: Where are my promo codes?

Question 28 of 45

True or false
Ally (Developer)
The weekend planner is ready mid-Sprint.

True or false: it can be released before the Sprint Review.

Learn it on Day 15: Release decision

Question 29 of 45

Choose 1
Arvid (Developer)
“Festival-goers can plan their weekend” is on the backlog, but nobody has asked festival-goers what they need.

What do you do before it's selected?

Learn it on Day 13: Questions from the team
Harbourfest

Sprint 3

Goal: the site plan is approved by the city

Question 30 of 45

Choose 1
Anthony (Festival Director)
Let's add a fireworks show!

It's costly, adds safety risk and doesn't serve the Product Goal. What do you do?

Learn it on Day 18: Does it fit the vision?

Question 31 of 45

Choose 1
Abby (Developer)
We rushed the power plan. It works on paper but has no backup.

What do you do?

Learn it on Day 19: The team wants to refactor

Question 32 of 45

Choose 1
Anthony (Festival Director)
Sponsors, the city and the crew each say their idea is the top priority.

Which technique reveals what they really value?

Learn it on Day 18: Does it fit the vision?

Technique: Buy a feature

Question 33 of 45

Choose 1
Aziz (Scrum Master)
Abby (Developer) and Ally (Developer) argue about where the food stalls go.

What helps most?

Learn it on Day 22: Overtime pressure

Question 34 of 45

Choose 1
Aziz (Scrum Master)
Evidence-Based Management check.

Every change to the site plan needs a three-week city review. Which area suffers?

Learn it on Day 16: Learning from real users

Question 35 of 45

True or false
Archer (Safety Officer)
Can I write the safety-related backlog items?

True or false: the Product Owner can delegate this but stays accountable.

Learn it on Day 13: Questions from the team

Question 36 of 45

Choose 1
Aziz (Scrum Master)
Arvid (Developer) told the Director a headliner deal was falling apart, early.

Which Scrum value did he show?

Learn it on Day 12: The CEO has an idea

Question 37 of 45

Choose 1
Ayaan (City Events Officer)
A new regulation bans stages on the east pier. Your Sprint Goal is the east-pier stage plan.

What do you do?

Learn it on Day 8: A request on the go

Question 38 of 45

Choose 1
Ally (Developer)
Archer (Safety Officer) wants changes to the site plan that mean redoing our map. Some of the team are rolling their eyes at him.

What's the right attitude?

Learn it on Day 22: Overtime pressure
Harbourfest

Festival and beyond

Goal: a safe, sold-out first Harbourfest

Question 39 of 45

Choose 1
Aziz (Scrum Master)
The festival weekend is here.

How should the three live days be run?

Learn it on Day 16: Learning from real users

Question 40 of 45

Choose 2
Anthony (Festival Director)
How do we know Harbourfest succeeded?

Which two are good outcome measures?

Learn it on Day 3: Shape the vision

Question 41 of 45

Choose 1
Amelie (Festival-goer)
Last year I gave up queuing for food after 40 minutes.

How do you test whether a pre-order app would fix that?

Learn it on Day 16: Learning from real users

Technique: Hypotheses and experiments

Question 42 of 45

Choose 1
Amelie (Festival-goer)
Could there be a winter edition?

What does this represent?

Learn it on Day 23: Thinking beyond v2

Question 43 of 45

Choose 1
Anthony (Festival Director)
Three weeks of 14-hour days before the festival?

What do you and Aziz (Scrum Master) advise?

Learn it on Day 22: Overtime pressure

Question 44 of 45

Choose 1
Anthony (Festival Director)
Next year we'll have two teams.

How should they work?

Learn it on Day 25: Product complete

Question 45 of 45

True or false
Anthony (Festival Director)
Was Scrum the right choice?

True or false: a good Product Owner knows where empiricism helps and where a simple plan is enough.

Learn it on Day 16: Learning from real users