Public-sector service43 questions5 phases

CityPermit: a Product Owner case study

Riverton City Council handles building permits on paper, and decisions take months. A new law says residents must be able to apply online by 1 January, with a fixed budget. You're the Product Owner of CityPermit, in an organisation used to thick documents and sign-offs.

What this case study tests
Fixed deadline & budgetCancelling a SprintAccessibility in the DoDScrum in a traditional organisation

You're the Product Owner. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Team
Astrid (Product Owner)You
Aldo (Scrum Master)Coaches team and council
Amara (Developer)Forms and front end
Anders (Developer)Data and old council systems
Ayden (Developer)Payments and testing
Stakeholders
Alan (City Manager)Sponsor, reports to councillors
Aurora (Legal Advisor)Every word must be lawful
Arnav (Permit Officer)Processes applications today
Alba (Accessibility Lead)Services must work for everyone
Aisling (Resident)Wants to build a garden studio
CityPermit

Getting started

A traditional council meets Scrum

Question 1 of 43

Choose 1
Alan (City Manager)
The council expects a 200-page requirements document, approved before any work starts.

How do you respond?

Learn it on Day 1: You're hired

Question 2 of 43

Choose 1
Alan (City Manager)
A steering committee of seven department heads will act as Product Owner.

What's the best response?

Learn it on Day 12: The CEO has an idea

Question 3 of 43

Choose 1
Aurora (Legal Advisor)
The deadline is set by law, and the budget is fixed.

With a fixed date and budget, what stays flexible?

Learn it on Day 22: Overtime pressure

Question 4 of 43

Choose 1
Astrid (Product Owner)
Time to set a Product Goal.

Which is the best Product Goal?

Learn it on Day 3: Shape the vision

Question 5 of 43

Choose 2
Alba (Accessibility Lead)
Public services must meet accessibility and data-protection law.

Which two belong in the Definition of Done?

Learn it on Day 5: Agree how the team will work

Question 6 of 43

Choose 1
Arnav (Permit Officer)
My team is worried the online system will replace us.

What do you do?

Learn it on Day 2: Meet the stakeholders

Question 7 of 43

Choose 1
Alan (City Manager)
Let's do three-month Sprints to match council meetings.

What does the Scrum Guide say?

Learn it on Day 5: Agree how the team will work

Question 8 of 43

Choose 1
Astrid (Product Owner)
Where should the first Increment start?

What's a smart first slice?

Learn it on Day 4: Build and order the backlog

Question 9 of 43

True or false
Alan (City Manager)
So Aldo (Scrum Master) is the team's manager?

True or false: the Scrum Master assigns work to the Developers.

Learn it on Day 1: You're hired

Question 10 of 43

Choose 1
Alan (City Manager)
Legal, accessibility and the permit officers will each review the system in their own phase after the developers finish. That's how the council works.

What do you propose?

Learn it on Day 11: Sprint 2 Planning
CityPermit

Sprint 1

Goal: residents can check whether their project needs a permit

Question 11 of 43

Choose 1
Amara (Developer)
You hoped for seven items. We think four can be Done this Sprint.

What do you do?

Learn it on Day 6: Sprint 1 Planning

Question 12 of 43

Choose 1
Alba (Accessibility Lead)
A screen reader can't use the checker form yet.

The Definition of Done includes accessibility. Is it Done?

Learn it on Day 24: Final checks

Question 13 of 43

Choose 1
Aurora (Legal Advisor)
I need to approve every sentence, and my approvals take three weeks.

What helps most?

Learn it on Day 17: A licence problem

Question 14 of 43

Choose 1
Alan (City Manager)
The council wants a 12-month plan: every feature with its month.

What do you offer instead?

Learn it on Day 3: Shape the vision

Technique: Product roadmap (now, next, later)

Question 15 of 43

Choose 2
Aldo (Scrum Master)
Let's understand the Sprint Goal better.

Which two statements are true?

Learn it on Day 6: Sprint 1 Planning

Question 16 of 43

Choose 1
Aisling (Resident)
I tried the checker. What on earth does “curtilage” mean?

What do you do with this feedback?

Learn it on Day 10: Review and Retrospective

Question 17 of 43

True or false
Alan (City Manager)
So the Sprint Review is where the steering committee signs off the work?

True or false.

Learn it on Day 10: Review and Retrospective

Question 18 of 43

Choose 1
Aldo (Scrum Master)
Retrospective idea: involve legal earlier in refinement.

When can the team act on it?

Learn it on Day 20: Release v1.1

Question 19 of 43

Choose 1
Alan (City Manager)
I'd like a written status report every morning instead of that standing meeting. It's how I keep the councillors informed.

How do you handle it?

Learn it on Day 7: A blocker on day two
CityPermit

Sprint 2

Goal: residents can apply online for a garden-building permit

Question 20 of 43

Choose 1
Aurora (Legal Advisor)
Breaking news: a new national law abolishes permits for small garden buildings, effective today.

This Sprint's goal is the garden-building application. What do you do?

Learn it on Day 8: A request on the go

Question 21 of 43

Choose 1
Amara (Developer)
The Sprint is cancelled. Now what?

What happens next?

Learn it on Day 6: Sprint 1 Planning

Question 22 of 43

Choose 1
Alan (City Manager)
Does the Product Goal change as well?

The Product Goal is “Residents can apply for a simple building permit fully online by 1 January”.

Learn it on Day 23: Thinking beyond v2

Question 23 of 43

Choose 1
Alan (City Manager)
Half the budget is spent. What percentage is complete?

How do you show progress honestly?

Learn it on Day 14: Where are my promo codes?

Question 24 of 43

Choose 2
Alan (City Manager)
What can Aldo (Scrum Master) do for the wider council?

Which two are Scrum Master services to the organisation?

Learn it on Day 7: A blocker on day two

Question 25 of 43

Choose 1
Alan (City Manager)
Councillors want a dashboard with permit statistics before the election.

It doesn't serve the Product Goal. What do you do?

Learn it on Day 18: Does it fit the vision?

Question 26 of 43

Choose 1
Anders (Developer)
To go faster we could take shortcuts in the data model. It'll hurt later.

What do you do?

Learn it on Day 19: The team wants to refactor

Question 27 of 43

Choose 1
Amara (Developer)
Extension permits are Done. Should real residents use them before 1 January?

What do you decide?

Learn it on Day 15: Release decision

Question 28 of 43

Choose 1
Anders (Developer)
The Product Backlog has 140 items, most copied from the old paper forms. Half of them nobody has looked at in months.

What do you do?

Learn it on Day 13: Questions from the team
CityPermit

Sprint 3

Goal: residents can pay fees and track their application

Question 29 of 43

Choose 1
Ayden (Developer)
The payment provider contract takes eight weeks through procurement.

How is this handled?

Learn it on Day 17: A licence problem

Question 30 of 43

Choose 1
Arnav (Permit Officer)
My officers want every online application printed on paper too.

How do you decide?

Learn it on Day 4: Build and order the backlog

Question 31 of 43

Choose 2
Aldo (Scrum Master)
Public-sector pressure tests our values.

Which two behaviours reflect Scrum values?

Learn it on Day 12: The CEO has an idea

Question 32 of 43

True or false
Alan (City Manager)
Even with a legal deadline, do the Developers still decide how much they can do?

True or false.

Learn it on Day 6: Sprint 1 Planning

Question 33 of 43

Choose 1
Anders (Developer)
40% of residents abandon their application at the document upload step.

What do you do?

Learn it on Day 16: Learning from real users

Question 34 of 43

Choose 1
Alan (City Manager)
The council meets next week. Will everything be ready by 1 January?

How do you answer?

Learn it on Day 14: Where are my promo codes?

Question 35 of 43

Choose 1
Ayden (Developer)
Some of us want to work weekends until the deadline.

What do you and Aldo (Scrum Master) advise?

Learn it on Day 22: Overtime pressure

Question 36 of 43

Choose 1
Aurora (Legal Advisor)
Every release needs a two-month council approval round.

Which Evidence-Based Management area suffers?

Learn it on Day 16: Learning from real users
CityPermit

Deadline and beyond

Goal: CityPermit meets the 1 January law

Question 37 of 43

Choose 1
Alan (City Manager)
It's 1 January. The core permits work online; a few extras aren't finished.

What do you do?

Learn it on Day 15: Release decision

Question 38 of 43

True or false
Alan (City Manager)
The deadline is legal. Can we release the unfinished parts too?

True or false: undone work may be released when the deadline is legally binding.

Learn it on Day 24: Final checks

Question 39 of 43

Choose 1
Alan (City Manager)
I want one quality standard for every digital service in the council.

How does it relate to Scrum Teams?

Learn it on Day 5: Agree how the team will work

Question 40 of 43

Choose 2
Alan (City Manager)
How do we prove CityPermit worked?

Which two are good outcome measures?

Learn it on Day 3: Shape the vision

Question 41 of 43

Choose 1
Aisling (Resident)
Could I also apply for a street-party permit online?

What does this represent?

Learn it on Day 23: Thinking beyond v2

Question 42 of 43

Choose 1
Arnav (Permit Officer)
The permit form is huge. We can't finish it in one Sprint.

How do you and the team split it?

Learn it on Day 11: Sprint 2 Planning

Technique: Story splitting

Question 43 of 43

True or false
Alan (City Manager)
Some say Scrum only works for software companies.

True or false: Scrum can't be used by public-sector organisations.

Learn it on Day 1: You're hired