Public-sector service 43 questions 5 phases
CityPermit: a Product Owner case study Riverton City Council handles building permits on paper, and decisions take months. A new law says residents must be able to apply online by 1 January, with a fixed budget. You're the Product Owner of CityPermit, in an organisation used to thick documents and sign-offs.
What this case study tests
Fixed deadline & budget Cancelling a Sprint Accessibility in the DoD Scrum in a traditional organisation
You're the Product Owner. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Team
Astrid (Product Owner) You Aldo (Scrum Master) Coaches team and council Amara (Developer) Forms and front end Anders (Developer) Data and old council systems Ayden (Developer) Payments and testing Stakeholders
Alan (City Manager) Sponsor, reports to councillors Aurora (Legal Advisor) Every word must be lawful Arnav (Permit Officer) Processes applications today Alba (Accessibility Lead) Services must work for everyone Aisling (Resident) Wants to build a garden studio CityPermit
Getting started A traditional council meets Scrum
Question 1 of 43 Choose 1
Alan (City Manager) The council expects a 200-page requirements document, approved before any work starts.
How do you respond? Write the 200-page document: it's how the council works, and a fight now would cost more time than writing it Incorrect. It would take months and still be wrong in places.Explain the empirical approach: agree a goal and an ordered backlog, then deliver working pieces for feedback Correct. Right. Scrum reduces risk by learning from real Increments, not documents.Explain that Scrum teams don't write documentation, so the council will have to change its rules Incorrect. Explain the alternative instead of rejecting the concern.
Learn it on Day 1: You're hired
Check answer
Question 2 of 43 Choose 1
Alan (City Manager) A steering committee of seven department heads will act as Product Owner.
What's the best response? One person is Product Owner; the committee are key stakeholders Correct. Right. The Product Owner is one person, not a committee.Accept it: a committee brings more expertise and opinions Incorrect. A committee blurs accountability and slows decisions.
Learn it on Day 12: The CEO has an idea
Check answer
Question 3 of 43 Choose 1
Aurora (Legal Advisor) The deadline is set by law, and the budget is fixed.
With a fixed date and budget, what stays flexible? Quality: a less polished first version can be improved later Incorrect. Quality doesn't decrease.Nothing: the law, date and budget fix everything in the plan Incorrect. Scope is the lever.Scope: you deliver the most valuable things first Correct. Right. Ordering by value matters most when time and money are fixed.
Learn it on Day 22: Overtime pressure
Check answer
Question 4 of 43 Choose 1
Astrid (Product Owner) Time to set a Product Goal.
Which is the best Product Goal? “Digitise the council's permit services and become a model for other cities.” Incorrect. Far too broad.“Complete and approve the full requirements for the online permit system.” Incorrect. A document isn't a product outcome.“Residents can apply for a simple building permit fully online by 1 January.” Correct. Right. Clear, user-focused, tied to the real constraint.
Learn it on Day 3: Shape the vision
Check answer
Question 5 of 43 Choose 2
Alba (Accessibility Lead) Public services must meet accessibility and data-protection law.
Which two belong in the Definition of Done? Meets the accessibility standard Correct. Correct.Meets data-protection requirements Correct. Correct.Signed off by the steering committee Incorrect. That's an approval gate, not a quality standard of the Increment.Printed for the paper archive Incorrect. Not a quality standard for the product.
Learn it on Day 5: Agree how the team will work
Check answer
Question 6 of 43 Choose 1
Arnav (Permit Officer) My team is worried the online system will replace us.
What do you do? Leave them out: the law decides what the system must do Incorrect. Resistance grows when people are ignored.Involve the permit officers early: their knowledge shapes it Correct. Right. They're key stakeholders and future users of the back office.
Learn it on Day 2: Meet the stakeholders
Check answer
Question 7 of 43 Choose 1
Alan (City Manager) Let's do three-month Sprints to match council meetings.
What does the Scrum Guide say? Sprints are one month or less in length Correct. Right. Longer cycles mean less feedback and more risk.Any length is fine if it's consistent Incorrect. The maximum is one month.
Learn it on Day 5: Agree how the team will work
Check answer
Question 8 of 43 Choose 1
Astrid (Product Owner) Where should the first Increment start?
What's a smart first slice? The simplest, most common permit type, so real residents can use it early Correct. Right. Early value and learning.All 14 permit types at once, so the law is met in full and no resident is left out Incorrect. Big-bang delivery delays everything.The internal admin reports, so officers are ready before residents start applying Incorrect. Residents get no value from that first.
Learn it on Day 4: Build and order the backlog
Check answer
Question 9 of 43 True or false
Alan (City Manager) So Aldo (Scrum Master) is the team's manager?
True or false: the Scrum Master assigns work to the Developers. True Incorrect. The Developers self-manage.False Correct. Correct. The Scrum Master coaches and removes impediments.
Learn it on Day 1: You're hired
Check answer
Question 10 of 43 Choose 1
Alan (City Manager) Legal, accessibility and the permit officers will each review the system in their own phase after the developers finish. That's how the council works.
What do you propose? A cross-functional team, with permit, accessibility and legal input inside every Sprint Correct. Right. Phase-by-phase reviews at the end leave no time to fix problems before the 1 January deadline.Follow the usual phases: the council trusts that process, and changing it now would cause friction Incorrect. Sequential reviews push all the risk to the end, just before a legal deadline.Do one combined review of everything in November, to leave the Developers free until then Incorrect. Legal and accessibility requirements are part of the law you must meet.
Learn it on Day 11: Sprint 2 Planning
Check answer
CityPermit
Sprint 1 Goal: residents can check whether their project needs a permit
Question 11 of 43 Choose 1
Amara (Developer) You hoped for seven items. We think four can be Done this Sprint.
What do you do? Accept their forecast and agree a Sprint Goal together Correct. Right. The Developers decide what they can get Done.Insist on seven, because the deadline is fixed Incorrect. Overloading leads to undone work.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 12 of 43 Choose 1
Alba (Accessibility Lead) A screen reader can't use the checker form yet.
The Definition of Done includes accessibility. Is it Done? Yes: it works, and accessibility can follow Incorrect. Done means the whole Definition of Done is met.No: without accessibility it isn't Done Correct. Right.
Learn it on Day 24: Final checks
Check answer
Question 13 of 43 Choose 1
Aurora (Legal Advisor) I need to approve every sentence, and my approvals take three weeks.
What helps most? Skip legal review for low-risk text, so only the important wording waits for Aurora Incorrect. Unlawful wording is a real risk.Aldo (Scrum Master) raises the barrier; bring Aurora (Legal Advisor) into refinement early Correct. Right. Remove the bottleneck rather than wait on it.Accept the three weeks and plan every item around them, since legal approval can't be rushed Incorrect. That breaks every Sprint.
Learn it on Day 17: A licence problem
Check answer
Question 14 of 43 Choose 1
Alan (City Manager) The council wants a 12-month plan: every feature with its month.
What do you offer instead? A now / next / later roadmap of outcomes, with the deadline marked Correct. Right. It shows direction and the fixed date without promising features nobody has learned about yet.A Gantt chart of every feature by month, since councillors expect it Incorrect. Dates for unknown work become promises you'll break.No plan: in Scrum the backlog is enough, and plans would change Incorrect. The council needs direction to plan.
Learn it on Day 3: Shape the vision Technique: Product roadmap (now, next, later)
Check answer
Question 15 of 43 Choose 2
Aldo (Scrum Master) Let's understand the Sprint Goal better.
Which two statements are true? It's the single objective for the whole Sprint Correct. Correct.It leaves flexibility in the exact work to achieve it Correct. Correct.The selected items can never change during the Sprint Incorrect. Scope can be renegotiated; the goal stays.The City Manager sets it for the team in advance Incorrect. The Scrum Team crafts it in Sprint Planning.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 16 of 43 Choose 1
Aisling (Resident) I tried the checker. What on earth does “curtilage” mean?
What do you do with this feedback? Add plain-language improvements to the backlog and order them Correct. Right. If residents don't understand it, it doesn't work.Keep the legal terms: the law requires that exact wording Incorrect. You can explain them in plain language.
Learn it on Day 10: Review and Retrospective
Check answer
Question 17 of 43 True or false
Alan (City Manager) So the Sprint Review is where the steering committee signs off the work?
Question 18 of 43 Choose 1
Aldo (Scrum Master) Retrospective idea: involve legal earlier in refinement.
When can the team act on it? After the next budget cycle approves the change Incorrect. Improvements shouldn't wait.As soon as the next Sprint, in its Sprint Backlog Correct. Right.
Learn it on Day 20: Release v1.1
Check answer
Question 19 of 43 Choose 1
Alan (City Manager) I'd like a written status report every morning instead of that standing meeting. It's how I keep the councillors informed.
How do you handle it? Have one Developer write a short report each morning after the Daily Scrum, so Alan gets his update Incorrect. That takes time from the work without improving any decision.The Daily Scrum is the Developers' 15-minute timebox, not a report; invite Alan to the Sprint Review Correct. Right. Daily written reports cost the Developers time; transparency through the backlog and the review gives him more.Replace the Daily Scrum with the written report, since councillors need written records anyway Incorrect. Then the Developers lose the daily plan they make together.
Learn it on Day 7: A blocker on day two
Check answer
CityPermit
Sprint 2 Goal: residents can apply online for a garden-building permit
Question 20 of 43 Choose 1
Aurora (Legal Advisor) Breaking news: a new national law abolishes permits for small garden buildings, effective today.
This Sprint's goal is the garden-building application. What do you do? The Sprint Goal is obsolete, so you, as Product Owner, may cancel the Sprint Correct. Right. This is exactly when cancelling is appropriate.Finish the Sprint anyway: the work may be reused for other permit types, and stopping wastes it Incorrect. Building something no one needs wastes the Sprint.Ask Aldo (Scrum Master) to cancel it, since he's responsible for how Scrum is run Incorrect. Only the Product Owner has that authority.
Learn it on Day 8: A request on the go
Check answer
Question 21 of 43 Choose 1
Amara (Developer) The Sprint is cancelled. Now what?
What happens next? Wait until the old Sprint's end date Incorrect. Start the next Sprint as soon as possible.A new Sprint Planning with a new Sprint Goal Correct. Right.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 22 of 43 Choose 1
Alan (City Manager) Does the Product Goal change as well?
The Product Goal is “Residents can apply for a simple building permit fully online by 1 January”. It's still valid: pick the next simple type, such as extensions Correct. Right. Only the Sprint Goal became obsolete.Abandon the Product Goal and set a new one for the year Incorrect. The overall goal still makes sense.
Learn it on Day 23: Thinking beyond v2
Check answer
Question 23 of 43 Choose 1
Alan (City Manager) Half the budget is spent. What percentage is complete?
How do you show progress honestly? Report 50%, since half the budget and half the time are used Incorrect. Money spent isn't progress.Show what residents can use now, plus a forecast from the backlog Correct. Right. Working product shows progress best.
Learn it on Day 14: Where are my promo codes?
Check answer
Question 24 of 43 Choose 2
Alan (City Manager) What can Aldo (Scrum Master) do for the wider council?
Which two are Scrum Master services to the organisation? Leading and coaching the council in adopting Scrum Correct. Correct.Removing barriers between stakeholders and teams Correct. Correct.Approving the project's budgets each year Incorrect. Not the Scrum Master's role.Writing the requirements documents for teams Incorrect. Not the Scrum Master's role.
Learn it on Day 7: A blocker on day two
Check answer
Question 25 of 43 Choose 1
Alan (City Manager) Councillors want a dashboard with permit statistics before the election.
It doesn't serve the Product Goal. What do you do? Say not now, with reasons tied to the Product Goal and deadline Correct. Right.Build it first: councillors' support matters for the whole project Incorrect. It would put the legal deadline at risk.
Learn it on Day 18: Does it fit the vision?
Check answer
Question 26 of 43 Choose 1
Anders (Developer) To go faster we could take shortcuts in the data model. It'll hurt later.
What do you do? Take the shortcuts quietly: the deadline is the law, and debt can wait Incorrect. Hidden debt grows.Discuss it openly; if debt is taken on, keep it visible and plan to reduce it Correct. Right.
Learn it on Day 19: The team wants to refactor
Check answer
Question 27 of 43 Choose 1
Amara (Developer) Extension permits are Done. Should real residents use them before 1 January?
What do you decide? Release now: residents get value and you learn before the deadline Correct. Right.Wait for the legal deadline and launch everything at once Incorrect. You'd lose months of feedback.
Learn it on Day 15: Release decision
Check answer
Question 28 of 43 Choose 1
Anders (Developer) The Product Backlog has 140 items, most copied from the old paper forms. Half of them nobody has looked at in months.
What do you do? Keep everything: each item came from a real paper form, and deleting them could upset the departments Incorrect. Old items crowd out what matters for the deadline.Ask the Developers to review all 140 items and pick the ones they think matter most for the deadline Incorrect. Ordering the backlog is the Product Owner's accountability.Remove or merge items that don't serve the 1 January goal, and keep refining the top ones with the Developers Correct. Right. A huge backlog hides what matters; ordering and refining keep attention on the law's deadline.
Learn it on Day 13: Questions from the team
Check answer
CityPermit
Sprint 3 Goal: residents can pay fees and track their application
Question 29 of 43 Choose 1
Ayden (Developer) The payment provider contract takes eight weeks through procurement.
How is this handled? Pause the payment work until procurement finishes, however long Incorrect. Look for other valuable work.Aldo escalates the blocker; you weigh options such as bank transfer first Correct. Right. Work around it and remove it.
Learn it on Day 17: A licence problem
Check answer
Question 30 of 43 Choose 1
Arnav (Permit Officer) My officers want every online application printed on paper too.
How do you decide? Agree: the officers are the users, and printing builds their trust in the new system Incorrect. Listen, then decide on value.Say no: printing undoes the point of an online system and wastes paper Incorrect. There may be a real need behind it.Understand why, consider a temporary solution, decide on value and explain Correct. Right.
Learn it on Day 4: Build and order the backlog
Check answer
Question 31 of 43 Choose 2
Aldo (Scrum Master) Public-sector pressure tests our values.
Which two behaviours reflect Scrum values? Being open with councillors about delays Correct. Correct: openness.Respecting the permit officers' expertise Correct. Correct: respect.Hiding delays to avoid political trouble Incorrect. That breaks openness and courage.Committing to fixed scope whatever happens Incorrect. Commitment is to goals, not impossible scope.
Learn it on Day 12: The CEO has an idea
Check answer
Question 32 of 43 True or false
Alan (City Manager) Even with a legal deadline, do the Developers still decide how much they can do?
True or false. True Correct. Correct. Deadlines are met by ordering value, not overloading the team.False Incorrect. The Developers always select what they can get Done.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 33 of 43 Choose 1
Anders (Developer) 40% of residents abandon their application at the document upload step.
What do you do? It's residents' computer skills: add a help page and move on Incorrect. The product must work for its users.Investigate why, and adapt the backlog based on the evidence Correct. Right. Inspect and adapt.
Learn it on Day 16: Learning from real users
Check answer
Question 34 of 43 Choose 1
Alan (City Manager) The council meets next week. Will everything be ready by 1 January?
How do you answer? A forecast from progress: what will be ready, and what might not Correct. Right. Honest forecasts help them plan.Yes, everything, guaranteed: the team will make sure of it Incorrect. False certainty.
Learn it on Day 14: Where are my promo codes?
Check answer
Question 35 of 43 Choose 1
Ayden (Developer) Some of us want to work weekends until the deadline.
What do you and Aldo (Scrum Master) advise? Accept the weekends: the deadline is set by law Incorrect. Burnout and bugs follow.A sustainable pace: scope is the lever to pull Correct. Right.
Learn it on Day 22: Overtime pressure
Check answer
Question 36 of 43 Choose 1
Aurora (Legal Advisor) Every release needs a two-month council approval round.
CityPermit
Deadline and beyond Goal: CityPermit meets the 1 January law
Question 37 of 43 Choose 1
Alan (City Manager) It's 1 January. The core permits work online; a few extras aren't finished.
What do you do? Delay the launch until every extra is complete and tested Incorrect. You'd miss the legal deadline.Launch what is Done and meets the law; extras stay in the backlog Correct. Right. Value first, nothing undone.
Learn it on Day 15: Release decision
Check answer
Question 38 of 43 True or false
Alan (City Manager) The deadline is legal. Can we release the unfinished parts too?
True or false: undone work may be released when the deadline is legally binding. True Incorrect. Undone work can't be part of the Increment or released.False Correct. Correct.
Learn it on Day 24: Final checks
Check answer
Question 39 of 43 Choose 1
Alan (City Manager) I want one quality standard for every digital service in the council.
How does it relate to Scrum Teams? It becomes the council's standard; every team's Definition of Done includes it Correct. Right.Teams may ignore it if their own Definition of Done is stricter Incorrect. Organisational standards apply to every team.
Learn it on Day 5: Agree how the team will work
Check answer
Question 40 of 43 Choose 2
Alan (City Manager) How do we prove CityPermit worked?
Which two are good outcome measures? Average days to a permit decision Correct. Correct.Share of applications made online Correct. Correct.Number of pages of documentation Incorrect. Output.Number of meetings held with staff Incorrect. Effort, not value.
Learn it on Day 3: Shape the vision
Check answer
Question 41 of 43 Choose 1
Aisling (Resident) Could I also apply for a street-party permit online?
What does this represent? Out of scope: CityPermit only does permits Incorrect. The service can grow.Unrealised value for a future Product Goal Correct. Right.
Learn it on Day 23: Thinking beyond v2
Check answer
Question 42 of 43 Choose 1
Arnav (Permit Officer) The permit form is huge. We can't finish it in one Sprint.
How do you and the team split it? Build the screens this Sprint and the back end next, so each layer gets full attention Incorrect. Neither half is usable on its own.Keep the form whole and make this Sprint longer, so it's finished properly in one go Incorrect. Sprints are fixed length.The simplest permit type end to end first (a garden shed), then more permit types Correct. Right. A thin vertical slice gives residents something usable and the team real feedback.
Learn it on Day 11: Sprint 2 Planning Technique: Story splitting
Check answer
Question 43 of 43 True or false
Alan (City Manager) Some say Scrum only works for software companies.
True or false: Scrum can't be used by public-sector organisations. True Incorrect. Scrum is for complex problems in any organisation.False Correct. Correct.
Learn it on Day 1: You're hired
Check answer