Day in the RoleQuality inspection checklistChecked against the requirements
DeliverableVentilation, treatment rooms 1 to 8
LocationRiverside clinic, ground floor
DateWeek 18
InspectorAntonia (Compliance Lead)
Checks
| Check | Against (requirement) | Pass | Fail | Notes |
|---|
| Duct size matches design, rooms 1–3 | Design drawing M-04 rev C | ✓ | | |
| Duct size matches design, rooms 4–6 | Design drawing M-04 rev C | | ✓ | Undersized: rev B used |
| Duct size matches design, rooms 7–8 | Design drawing M-04 rev C | ✓ | | |
| Air changes per hour | At least 6 per hour | ✓ | | Measured 7 |
| Filters fitted and labelled | Infection-control spec 3.2 | ✓ | | |
| Access panels for cleaning | One per room | ✓ | | |
Defects to fix
| Defect | Owner | Fix by | Re-checked |
|---|
| Replace ducts, rooms 4–6 | Arash (Contractor) | Week 19 | |
| Confirm all trades have drawing rev C | Arash (Contractor) | Week 18 | ✓ |
Pass: acceptedPass with minor defectsFail: fix and re-inspect