← Root cause verification: explanationFilled-in example Blank template
Day in the RoleRoot cause verificationWhich causes are proven, and how
Version1.0
Date15 March

Result: proven (data shows it drives the result, with a clear mechanism) · likely (strong signs, not yet tested) · ruled out (data shows it doesn't).

Suspected causeHow testedEvidenceResult
Only today's slots released, at 8 am5 whys; booking data38% of first requests told to call back; 2.1 days addedProven
Two doctor sessions lost from week 12Two-sample t-test; Mann-WhitneyWeekly median wait +3.3 days; p below 0.0001Proven
Monday demand meets flat capacityANOVA; Kruskal-Wallis; Mood's median; FriedmanMonday 15.9 days against 6.4 to 10.2; worst every weekProven
No reminders for phone bookingsTwo-proportion test; chi-squareMissed 19.0% without against 8.1% with; missed rises with waitProven (pilot to confirm)
Urgent cases use routine slotsFMEAHighest risk score (252); not yet measuredLikely: measure in Improve
Some doctors are slowerMulti-variDoctor averages within 1.3 daysRuled out

How the causes link

Long waits lead to more missed appointments (6% to 29%), which waste slots and make waits longer.

Project leader
Signature
Date
Sponsor
Signature
Date

Letters and symbols: ANOVA Analysis of variance: a test that compares the averages of three or more groups · FMEA Failure modes and effects analysis