| Version | 1.0 |
|---|---|
| Date | 15 March |
Patients waited a median of 10 days for a routine appointment; 1 in 4 over 14. Goal: median 5 days or less, 90% within 7 days, in five months.
Swimlane map and value stream (19 minutes of work in 10.4 days). Measurement checked: attribute agreement 95%, gauge 13.8%. Baseline: 55% over 7 days, sigma level 1.4.
Proven: same-day slot release (call-back loop), two lost doctor sessions since week 12 (+3.3 days), Monday demand on flat capacity, no reminders for phone bookings (missed 19% against 8%). Urgent use of routine slots confirmed by regression.
Book up to 2 weeks ahead, reminders for every booking, protected urgent slots with a system lock, two extra Monday sessions, cover for lost sessions. Pilot: median 4 days, 88% within 7, missed 8.5%.
Control plan with six charted measures and a response plan, owned by Aurelie. After roll-out: 91% within 7 days, median 4. Benefits €36,705 a year, confirmed by finance; payback about 9 months.
| Measure | Before |
|---|---|
| Median wait | 10 days |
| Within 7 days | 45% |
| Missed | 15.7% |
| Sigma level | 1.4 |
| Measure | After |
|---|---|
| Median wait | 4 days |
| Within 7 days | 91% |
| Missed | 8.3% |
| Sigma level | about 2.8 |
Next project from the opportunity log: telling patients when their test results are back.
Letters and symbols: CUSUM Cumulative sum chart: adds up differences from the target to catch small shifts · EWMA Exponentially weighted moving average chart