← Document and drawing register: explanationFilled-in example Blank template
Day in the RoleDocument and drawing registerOne register of current versions
Version1.0
Date15 March
Document or drawingVersionStatusIssuedChanged becauseConfirmed by
Floor planv8ApprovedWeek 22Walls moved (CR-07)All trades
Floor planv6WithdrawnWeek 14Superseded
Ventilation layoutrev DApprovedWeek 22Walls movedContractor, ventilation
Electrical layoutrev FApprovedWeek 23Sockets movedElectricians
Booking system settings1.4ApprovedWeek 25One-click follow-upVendor, IT

Status: draft · approved · withdrawn. Withdrawn versions are removed from site and shared folders.

Letters and symbols: CR Change request (CR-07 = change request number 7) · IT Information technology