| Version | 1.0 |
|---|---|
| Date | 15 March |
| Group (number) | Booking system | Infection control | Fire safety | Patient flow | How readiness is checked | Ready |
|---|---|---|---|---|---|---|
| Reception (6) | Wk 26 | Wk 27 | Wk 27 | Five practice bookings each | ||
| Nurses (12) | Wk 26 | Wk 25 | Wk 27 | Wk 27 | Observed practice | |
| Doctors (6) | Wk 26 | Wk 25 | Wk 27 | Observed practice | ||
| Healthcare assistants (4) | Wk 25 | Wk 27 | Wk 27 | Observed practice |
Write the week each group takes each course. Ready = they have shown they can do it, not just attended.
Letters and symbols: Wk · M1 Week and month numbers in schedules (Wk 26 = week 26, M3 = month 3)