Day in the RoleResource planWho's needed when, and how much
Load per month (% of their time on the project)
| Person | M1 | M2 | M3 | M4 | M5 | M6 | M7 |
|---|
| Antonia (Compliance Lead) | 40% | 50% | 60% | 80% | 95% | 70% | 60% |
| Aine (IT Lead) | 50% | 60% | 80% | 80% | 90% | 60% | 40% |
| Adaugo (HR Lead) | 20% | 40% | 60% | 60% | 60% | 40% | 20% |
| Aya (Coordinator) | 80% | 90% | 90% | 90% | 90% | 90% | 80% |
| Anwar (Facilities) | 10% | 30% | 60% | 70% | 80% | 90% | 60% |
Shade cells above 90% lightly and above 100% darker. Include holidays and other duties.
Peaks and how we fixed them
| Person | When | Load | Fix |
|---|
| Antonia | Month 5 | 160% → 95% | Two tasks with float moved; one inspection by the council team |
| Aine | Month 5 | Holiday during testing | Holiday moved to month 7 by agreement |
Letters and symbols: HR Human resources · IT Information technology · Wk · M1 Week and month numbers in schedules (Wk 26 = week 26, M3 = month 3)