← Resource plan: explanationFilled-in example Blank template
Day in the RoleResource planWho's needed when, and how much
Version1.0
Date15 March

Load per month (% of their time on the project)

PersonM1M2M3M4M5M6M7
Antonia (Compliance Lead)40%50%60%80%95%70%60%
Aine (IT Lead)50%60%80%80%90%60%40%
Adaugo (HR Lead)20%40%60%60%60%40%20%
Aya (Coordinator)80%90%90%90%90%90%80%
Anwar (Facilities)10%30%60%70%80%90%60%

Shade cells above 90% lightly and above 100% darker. Include holidays and other duties.

Peaks and how we fixed them

PersonWhenLoadFix
AntoniaMonth 5160% → 95%Two tasks with float moved; one inspection by the council team
AineMonth 5Holiday during testingHoliday moved to month 7 by agreement

Letters and symbols: HR Human resources · IT Information technology · Wk · M1 Week and month numbers in schedules (Wk 26 = week 26, M3 = month 3)

Day in the Role · Resource planIllustrative example · not a real project or organisation · dayintherole.com