← Project charter: explanationFilled-in example Blank template
Day in the RoleProject charterAuthorisation to start the project
Version1.0
Date15 March

This charter formally starts the project below and gives the project manager authority to use the resources described. It is signed by the sponsor.

ProjectRiverside Health Centre
Start date1 April
SponsorAtticus (Director of Community Health)
Project managerAnnelise (Project Manager)

Objective

Outcome
Residents of Riverside get everyday care within 15 minutes of home
Measure
GP waiting time under 1 week
By when
Clinic open in month 7; target within 1 year of opening

In scope

  • Building conversion
  • Equipment
  • Booking system
  • Hiring and training
  • Licence to open

Out of scope

  • Emergency care
  • Hospital beds
  • Pharmacy (possible later)

Key milestones

Design approvedMonth 1
Building works doneMonth 5
Licence grantedMonth 6
Clinic opensMonth 7

Budget, time and scope tolerances

ApprovedTolerance
Budget€4.2M± €25k without escalation
TimeOpening in month 7± 2 weeks within a stage
ScopeAs aboveNo change without approval

Authority of the project manager

Detail
May decide aloneSpending up to €25,000; schedule changes within a stage
Must escalate to the sponsorAnything larger, any change to the opening date or scope

Key stakeholders

NameRoleInvol­vement
Atticus (Sponsor)SponsorDecides, owns the budget
Amani (Clinical Lead)Clinical leadDefines clinical needs, accepts the clinic
Abigail (Finance)FinanceApproves spending
Azadeh (Community Council)Community councilVoice of residents
SponsorAtticus (Director of Community Health)
Signature
Date
Project managerAnnelise (Project Manager)
Signature
Date

Letters and symbols: GP General practitioner: a family doctor · ± Plus or minus: the allowed range either side · €k Thousands of euros (€150k = €150,000) · €M Millions of euros (€4.2M = €4,200,000)

Day in the Role · Project charterIllustrative example · not a real project or organisation · dayintherole.com