Day in the RoleProject charterAuthorisation to start the project
This charter formally starts the project below and gives the project manager authority to use the resources described. It is signed by the sponsor.
ProjectRiverside Health Centre
Start date1 April
SponsorAtticus (Director of Community Health)
Project managerAnnelise (Project Manager)
Objective
OutcomeResidents of Riverside get everyday care within 15 minutes of home
MeasureGP waiting time under 1 week
By whenClinic open in month 7; target within 1 year of opening
In scope
- Building conversion
- Equipment
- Booking system
- Hiring and training
- Licence to open
Out of scope
- Emergency care
- Hospital beds
- Pharmacy (possible later)
Key milestones
Design approvedMonth 1
Building works doneMonth 5
Licence grantedMonth 6
Clinic opensMonth 7
Budget, time and scope tolerances
| Approved | Tolerance |
|---|
| Budget | €4.2M | ± €25k without escalation |
|---|
| Time | Opening in month 7 | ± 2 weeks within a stage |
|---|
| Scope | As above | No change without approval |
|---|
Authority of the project manager
| Detail |
|---|
| May decide alone | Spending up to €25,000; schedule changes within a stage |
|---|
| Must escalate to the sponsor | Anything larger, any change to the opening date or scope |
|---|
Key stakeholders
| Name | Role | Involvement |
|---|
| Atticus (Sponsor) | Sponsor | Decides, owns the budget |
| Amani (Clinical Lead) | Clinical lead | Defines clinical needs, accepts the clinic |
| Abigail (Finance) | Finance | Approves spending |
| Azadeh (Community Council) | Community council | Voice of residents |
SponsorAtticus (Director of Community Health) Project managerAnnelise (Project Manager)
Letters and symbols: GP General practitioner: a family doctor · ± Plus or minus: the allowed range either side · €k Thousands of euros (€150k = €150,000) · €M Millions of euros (€4.2M = €4,200,000)