Day in the RoleLessons reportWhat the next project should know
ProjectRiverside Health Centre
Worked well: repeat
- Safety-first decisions on site
- Early engagement after the newspaper story
- Drawing revision log
- Phone booking fallback planned in advance
Didn't work: avoid
- Slow job offers lost a key candidate
- The council's own security upgrade surprised everyone
- Inspection backlog spotted late
Recommendations for future projects
1Book external dependencies first
WhyPurchases, inspections and system upgrades caused every major delay
ForAll projects with outside approvals 2Set offer deadlines before hiring starts
WhyA 3-week contract lost our best lead nurse
ForProjects that hire 3Pair people on critical systems
WhyOne resignation put integration at risk
ForProjects with IT work 4Agree status colour rules on day one
WhyA green dashboard hid failing tests for weeks
ForAll projects
Letters and symbols: IT Information technology