Day in the RoleImplementation planFrom pilot to normal work
Version1.0
Date15 March

Tasks

TaskOwnerBy whenDone
Booking up to 2 weeks ahead for all staffAlma (Reception Team Lead)Week 1✓
System lock on urgent slotsAstrid (Data Analyst)Week 1✓
Monday sessions in the rotaAurelie (Practice Nurse Manager)Week 2✓
Reminders for every bookingAstrid (Data Analyst)Week 1✓
Recruit cover for 2 sessionsAurelie and AtticusWeek 4
Weekly results to the teamAmara (Process Improvement Specialist)Weekly

Training and communication

AudienceMessage or skillHowWhen
ReceptionistsNew booking script1-hour trainingWeek 1
DoctorsPilot results, what changesTeam meeting, pilot doctors speakWeek 1
PatientsBook ahead, remindersPosters, website, textWeek 1
CouncilResults so farAtticus's reportWeek 4

Risks

  • Cover not found in time
  • Thursday waits grow
  • Old habits return

How we'll know it worked

90% offered an appointment within 7 days and median 5 days or less, measured weekly from week 2.

Process owner
Signature
Date
Sponsor
Signature
Date