| Version | 1.0 |
|---|---|
| Date | 15 March |
| Item | Year 0 | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | Total |
|---|---|---|---|---|---|---|---|
| Costs | |||||||
| Building conversion | 3,100 | 3,100 | |||||
| Equipment | 700 | 700 | |||||
| IT and booking system | 200 | 200 | |||||
| Opening and hiring | 200 | 200 | |||||
| Staff and running costs | 1,900 | 1,900 | 1,900 | 1,900 | 1,900 | 9,500 | |
| Total costs | 4,200 | 1,900 | 1,900 | 1,900 | 1,900 | 1,900 | 13,700 |
| Benefits | |||||||
| Regional health funding | 1,600 | 1,600 | 1,600 | 1,600 | 1,600 | 8,000 | |
| Fewer minor emergency visits | 900 | 900 | 900 | 900 | 900 | 4,500 | |
| Total benefits | 0 | 2,500 | 2,500 | 2,500 | 2,500 | 2,500 | 12,500 |
| Net (benefits − costs) | -4,200 | 600 | 600 | 600 | 600 | 600 | -1,200 |
| Cumulative | -4,200 | -3,600 | -3,000 | -2,400 | -1,800 | -1,200 | |
About 7 years
When the cumulative line turns positive.
| If this happens | The result becomes |
|---|---|
| Building costs +20% | Payback about 8 years |
| Benefits start 6 months late | Payback about 7.5 years |
| Funding −10% | Payback about 9.5 years |
Letters and symbols: IT Information technology · €k Thousands of euros (€150k = €150,000)