Day in the RoleAcceptance certificateChecked, accepted, handed over
DeliverableConverted building, Riverside clinic
SupplierBuilding contractor (RHC-SOW-01)
DateWeek 26
Accepted with conditions
Checked against the agreed criteria
| Acceptance criterion | Result | Evidence |
|---|
| Building-control sign-off | MetNot met | Certificate BC-2231 |
| Ventilation to design (rev D) | MetNot met | Re-inspection, week 25 |
| Wheelchair routes in all patient areas | MetNot met | Walk-through with Amani (Clinical Lead) |
| Infection-control surfaces | MetNot met | Antonia (Compliance Lead)'s checklist |
| Fire safety certificate | MetNot met | Fire officer, week 26 |
Outstanding minor defects
| Defect | Fix by | Owner |
|---|
| Room signs missing | Week 27 | Arash (Contractor) |
| Two door closers too strong | Week 27 | Arash (Contractor) |
| Paint touch-ups, corridor | Week 28 | Arash (Contractor) |
Result
AcceptedAccepted with conditionsNot accepted
Payment held back10% held until all defects are closed
Accepted by (user side)Amani (Clinical Lead)
Letters and symbols: RHC Riverside Health Centre (used as a reference prefix, like RHC-SOW-01)